by Eko Prasetyo @ 7:13 AM ![]() The valves were put in wrong positions by the drilling crew, and the wellservice guys needed to manually relocated them so that the well can be put into proper production state. The supply control panel shows that the power used are somewhat below standard, so the seasoned engineers needed to know whether the panel were already calibrated or not. Well..no smooth start for this one, that's for sure |